Manor Farm, Bessingham

Manor Farm, Bessingham

Conservation area consent was required to demolish the existing building and provide for a new four bedroomed replacement dwelling. The project was designed with large, well-lit, open areas. The foundations were piled and suspended floors installed. Materials salvaged from the demolition were integrated into the design and local materials were used by local craftsmen. A waste and surface water management system was included in the design.

Project associate:

David Stead RIBA

Main contractor:

Morrissey Builders Ltd.

Agents (consultants etc):

John Robinson Associates

Project value:

£500,000 approx